Process

Seven steps. No shortcuts. Built to outlast the building.

Every Antonio Terrazzo install follows the same documented sequence — from preconstruction gates through the final polish and maintenance handoff. Here's what happens on your floor, in order, with the durations you can plug into your CPM schedule.

  1. Step 01

    Preconstruction

    Weeks −6 to −2 before pour

    Spec review, divider-strip layout against the architectural plan, sample sign-off, schedule alignment with the GC, and gate review for slab readiness (age, MVER target, building dried-in, HVAC operational). We don't mobilize until each gate is verifiably green.

  2. Step 02

    Substrate prep

    Days 1–2

    Mechanical shot-blasting or diamond grinding to ICRI CSP-3 to CSP-4 profile, crack chase and fill with rigid epoxy, and removal of any bond-breakers (sealers, curing compounds, paint). We test the prepped slab with a tape-pull before priming.

  3. Step 03

    Moisture mitigation

    Day 2 (if required)

    ASTM F2170 in-situ RH probes at three locations per 1,000 sq ft. If readings exceed 75% RH, we apply a 100%-solids epoxy MVB rated to 100% RH before priming. We document every probe reading in the closeout package.

  4. Step 04

    Divider strip layout

    Days 3–4

    Snap layout to the approved divider drawing, set zinc, brass, or aluminum L-angle strips in epoxy adhesive at every control joint and design line, and verify alignment with the architect's reflected ceiling plan if specified.

  5. Step 05

    Matrix pour

    Days 5–7

    Pre-batched pigmented epoxy matrix is hand-blended with the specified aggregate package, trowel-applied between dividers to 3/8" nominal thickness, and consolidated. Pour proceeds in panels sized to the project's thermal-movement plan.

  6. Step 06

    Grind, grout & re-grind

    Days 8–11 (24-hour cure between passes)

    Coarse-grit rough grind exposes aggregate. We grout-coat pinholes with matching matrix, cure 24 hours, then re-grind through progressively finer diamond grits (typically 50 → 100 → 200) until the surface is uniform.

  7. Step 07

    Polish & seal

    Days 12–13

    Final polish to the specified gloss (typically 400–800 grit), penetrating sealer, and a sacrificial finish coat if requested. Floor protection goes down before we demobilize, and the owner gets a printed maintenance guide.

Process variations by system

The sequence shifts when the system shifts.

The seven steps above describe a poured-in-place epoxy terrazzo install. Our other systems share the discipline — preconstruction gates, moisture testing, mockups, and documented closeout — but the field sequence and durations differ. Quick orientation:

Pair with the specifications

Every step ties to a line in the spec.

The process above is what we do in the field. The specifications page is what your design team writes to make sure we do it — CSI 09 66 23 section text, ASTM references, divider details, and the submittal log we deliver within 14 days of award.

Cross-section of a finished epoxy terrazzo floor system